Renovating a luxury kitchen is an exciting journey, but one that requires careful planning and realistic expectations about timing. Creating your dream kitchen involves multiple steps, from design to installation, and understanding the timeframe can help you manage the process smoothly. So, how long does a luxury kitchen renovation take, and what can you expect along the way?
Initial Consultation & Design Phase (2-4 Weeks)
The process starts with an initial consultation, where you’ll discuss your vision, preferences, and needs with our design team. During this phase, we’ll help you select materials, appliances, and features that match your lifestyle and aesthetic goals. Depending on how refined your ideas are, this can take anywhere from two to four weeks, as you may want to explore different design options.
Key tasks:
- Meeting with designers to discuss the project
- Creating detailed plans and layout designs
- Selecting materials, finishes, and appliances
Approval & Ordering of Materials (4-6 Weeks)
Once the design is finalised, the next step is ordering materials. High-end finishes, bespoke cabinetry, and premium appliances are often custom-made, which can take time. Depending on the suppliers and complexity of your choices, the lead time for delivery can vary. Expect about four to six weeks for all your materials to arrive.
Key tasks:
- Final design approval
- Ordering bespoke cabinetry, worktops, and appliances
- Coordinating deliveries to align with the project schedule
Site Preparation & Demolition (1-2 Weeks)
Before the new kitchen can be installed, the existing space must be prepped. This typically involves demolition of the old kitchen, structural changes if needed, and preparing the utilities. If your project requires significant structural work, such as moving walls or plumbing, this could extend the timeline.
Key tasks:
- Demolition of the old kitchen
- Adjusting electrical and plumbing systems
- Potential structural work (e.g., moving walls)
Installation of Cabinets, Worktops & Appliances (4-6 Weeks)
This is the phase where your dream kitchen starts to take shape. First, cabinets are installed, followed by worktops, and finally, appliances. Bespoke and luxury kitchens often have intricate details, meaning the installation process can take longer than a standard kitchen.
Key tasks:
- Installing custom cabinetry
- Fitting worktops and splashbacks
- Appliance installation and integration
Finishing Touches & Inspections (1-2 Weeks)
Once the core elements are in place, it’s time for the finishing touches, such as lighting, painting, and any final adjustments. Your kitchen will undergo inspections to ensure everything is functioning properly and meets the high standards expected in a luxury renovation.
Key tasks:
- Finalising lighting, fixtures, and décor
- Painting and adding any custom finishes
- Quality control and inspection
Total Timeframe for a Luxury Kitchen Renovation: 3-4 Months
While each project varies, a typical luxury kitchen renovation takes between three and four months from start to finish. Custom elements, design revisions, or unexpected structural challenges may extend this timeline. However, with a clear plan and expert team, your dream kitchen can be brought to life efficiently and without compromising on quality.